Large-Scale Construction Waste Management for Kuwait National Cultural District Development

The Kuwait National Cultural District project generated exceptionally high volumes of construction waste across multiple phases, including excavation, structural works, and interior finishing. Sustainability targets required strict landfill diversion rates while maintaining uninterrupted construction progress within a dense urban environment.

Al Salsabil Co. developed a comprehensive construction waste management strategy incorporating phased dumpster deployment, on-site segregation zones, and just-in-time waste collection aligned with construction schedules. Each waste stream was handled separately to maximize recycling and recovery potential.

Advanced recycling partnerships, material recovery processes, and digital tracking systems enabled real-time monitoring of waste volumes, diversion rates, and compliance metrics. This approach ensured transparency, accountability, and continuous optimization throughout the project lifecycle.

Need Help? We Are Here To Help You

You Get Online support

Contact Us
project
project

Project Challenges

  1. Managing limited on-site space for waste containers and sorting operations.
  2. Coordinating waste management activities across multiple contractors and construction disciplines.
  3. Maintaining dust, noise, and environmental controls in a densely populated urban location.
project
project
project

Final Result

The project achieved an 85% landfill diversion rate, exceeded sustainability targets, and supported successful LEED certification. Efficient waste handling reduced operational disruptions, improved site safety, and set a new benchmark for large-scale construction waste management in Kuwait.